Year 1 of the program 

Pima County recently received bids for projects included in the first year of this program. Southern Arizona Paving was the low bidder for the work in the Sahuarita area. Southern Arizona Paving (SAP) was awarded the contract for the paving work in the Sahuarita area. 

Construction will begin on neighborhoods receiving a Scrub Seal with Fog Seal as follows:

Presidio de Valle (Scrub Seal): September 18-19, 2018
Presidio de Valle (Fog Seal): October 1-2, 2018
Rancho Buena Vista (Scrub Seal): September 20-21, 2018
Rancho Buena Vista (Fog Seal): October 3-4, 2018
La Canada Norte* (Scrub Seal): September 24, 2018
La Canada Norte* (Fog Seal): October 5, 2018
La Joya Verde* (Scrub Seal): September 25, 2018
La Joya Verde* (Fog Seal): October 8, 2018
Madera Highlands 1 and 3 (Scrub Seal): September 26-28, 2018
Madera Highlands 1 and 3 (Fog Seal): October 9-12, 2018

Construction will begin on neighborhoods receiving Microsurfacing as follows:

Presidio De La Madera: October 17, 18, and 22, 2018
Via Santo Tomas: October 23, 2018
Presidio de Cancion*: October 24-25, 2018
Presidio de Arboles*: October 29-30, 2018

Residents will be provided notice prior to the start of any construction. Door hangers notifying residents of construction will be distributed. 

The Town of Sahuarita will be funding local road preservation projects at this time. All locations marked with an asterisk (*) are funded by the Town of Sahuarita.

More details will be provided as we get closer to the start dates. 

Subdivisions/Roads Maps