Posted on: March 2, 2021

Pavement Preservation Projects

Town of Sahuarita - Pavement Preservation

Click here and enter your address to find out when your street is scheduled for maintenance.

Anticipated Spring schedule:

March 8 - 18: Crack seal La Canada

March 22 - April 1: Crack seal Sahuarita Road

April 10 - 11: Via Rancho Sahuarita

April 5 - 13: La Canada

April 12 - 20: Ranch Sahuarita Boulevard

April 19 - 27: Sahuarita Road

April 26 - 29: Abrego Drive

May 24-  June 4: Final Striping (all projects)


REVISED SCHEDULE (3/24/2021)

Due to wet weather and cooler temperatures, the paving schedule has been revised:
Town Hall – April 10-11
Sahuarita Road – thru April 22 (Crack Seal)
Sahuarita Road – May 24-28 (Paving)
La Canada – May 10-14 (Paving)
Rancho Sahuarita Blvd – May 17-21 (Paving)
Abrego – June 1-2 (Paving)



All of these projects will be completed using TRMSS which is a tire rubber modified asphalt emulsion surface treatment, that looks like and gets applied like a slurry seal but this pavement treatment contains more aggregate and has a higher rubber content than a traditional slurry seal.  As such it  provides better wear and weather resistance. 

 

This pavement treatment is also “greener” than the traditional alternative as using TRMSS diverts approximately 80 tires per lane mile from the landfill. These projects total just under 68 lane miles of road (or 5440 tires not going to the landfill).